How far each workstream has come, and the timeline of how the project got here. Percentages are working judgment calls against each track's own definition of done, not measurements.

By workstream

Web product — feature-complete except payments~85%
Payments / revenue — schema only, no checkout~15%
Mobile app — auth + read-only shell of a 17-module spec~20%
AWS migration — deployed and verified July 17; DNS cutover + parity soak remain~90%
Design refresh — comps produced, direction not chosen~25%
Concept validation — 3 test apps built, focus group not yet run~50%

Timeline

WhenMilestone
2025Lumenal web app built on Lovable (React + Supabase); launched at lumenal.ai with readings across eight belief systems, shop, social, gamification and admin console.
Jan 2026Product media shot (assets/); sample Solar Return report produced.
Feb 3-4, 2026Nine-document platform review written (docs/*.md): architecture, schema, APIs, features, admin, mobile spec and mobile design strategy.
Feb-Jun 2026lumenal_expo scaffolded and built to a Phase-1 shell — full theme system, auth, readings browsing — faithfully following the design-strategy doc.
Jul 10, 2026Full multi-agent review produced docs/index.html (canonical). Strategic decisions confirmed: AWS-native migration, direct Gemini API. CDK scaffold (infra/, 6 stacks) written and synth-verified against the target account.
Jul 17, 2026This reference site created: full inventory, 3 desktop + 4 mobile design comps, and 3 complete focus-group test apps (Daily, Guide, Deck) with built-in feedback capture.

What "done" means per track

Reading the chart honestly

The two tracks that matter most to the business — payments and mobile — are the two least advanced. That is the argument for the current plan: validate the mobile concept cheaply while payments get built, instead of resuming the 22-week mobile spec head-down.